Tag Archives: installing coverings

Installing Multiple Covers into One Wirelock Channel

This post covers another one of our most frequently asked questions,

HOW TO INSTALL MULTIPLE COVERS INTO ONE WIRELOCK CHANNEL!

We hope the description and video can help clarify this issue a bit more. Thanks for your feedback!

The beauty of wirelock is its ability to hold multiple layers of covers, even covers in different directions (i.e. roof and ends or 2 long lengths).

Before starting you must at least have the cover tacked at the opposite end. This will give you resistance for pulling the cover tight.

Our wirelock channel will hold up to 3 layers of 6 mil plastic securely.

Two layers of 12 mil tarp will not be held securely in the wirelock channel. This is why we recommend that the top of the end wall tarp be sandwiched between the channel and the hoop.

If you have never installed these covers before, it is recommended to use at least 3 people.

  • After the bottom of the end cover has been secured, pull the end cover over the hoop first.
  • Person “A” will hold it from the inside of the structure in such a way that there are no wrinkles.
  • The roof cover can now go over the channel as well.
  • Person “B” will pull on the roof cover while person “C” installs the stainless spring steel wire inserts.
  • “C” will start from the peak and work down.

It is critical to remember that “A” and “B”, who are pulling on the two respective covers, must always be pulling at least a foot ahead of “C” who is installing the wire insert. This will allow a little give in the covers so that there will not be damage.

With more experience “B” and “C” can be done by one person.

It is also important to remember the wrist technique for installing the wire insert. Do not slide the wire straight back and forth. This causes abrasions on the cover.

As you move back and forth, apply pressure with the thumb on the next parallel spot of the wire insert.
Use a needle nose pliers to get the last tip into the channel.
The next wire insert does not have to be overlapped.

For more details and to watch an illustration, please see our YouTube Video below

Installing Before Winter

There always seems to be so much pressure and panic at this time to get a building before winter. The only thing that is important to get done sooner then later is the foundation work. There will be lots of decent weather days between now and Christmas to get the job done.

If you think that it is too late to get it done and you will simply wait until next spring, please remember that you said the same thing last spring (or even a few months ago) and as usual the busyness of life got in the way. Give us a call today to see how you can get that foundation taken care of before freeze up.

For those of you who want to get the structure up now and cover it in the spring, I urge you to cover the building sooner then later for a couple of reasons. First is that there will be lots of other things vying for your time in the spring and secondly, the more snow you have on that spot which has to melt, the more moisture you will have in the building. The more moisture you have in the building the more condensation issues you will have. You want to give that ground the most time possible to dry up before you need to start using the building.

In my humble opinion, even though putting the cover on in late fall or early winter is more difficult and not pleasant, the benefits of having more time for the ground to dry, far outweigh the time spent to adjust the cover  in the spring

Installing Multiple Covers into One Wirelock Channel

This post covers another one of our most frequently asked questions, and we hope the description and video can help clarify this issue a bit more. Thanks for your feedback!

The beauty of wirelock is its ability to hold multiple layers of covers, even covers in different directions (i.e. roof and ends or 2 long lengths). Before starting you must at least have the cover tacked at the opposite end. This will give you resistance for pulling the cover tight. Our wirelock channel will hold up to 3 layers of 6 mil plastic securely. Two layers of 12 mil tarp will not be held securely in the wirelock channel. This is why we recommend that the top of the end wall tarp be sandwiched between the channel and the hoop.

If you have never installed these covers before, it is recommended to use at least 3 people. After the bottom of the end cover has been secured, pull the end cover over the hoop first. Person “A” will hold it from the inside of the structure in such a way that there are no wrinkles. The roof cover can now go over the channel as well.  Person “B” will pull on the roof cover while person “C” installs the stainless spring steel wire inserts. “C” will start from the peak and work down. It is critical to remember that “A” and “B”, who are pulling on the two respective covers, must always be pulling at least a foot ahead of “C” who is installing the wire insert. This will allow a little give in the covers so that there will not be damage. With more experience “B” and “C” can be done by one person.

It is also important to remember the wrist technique for installing the wire insert. Do not slide the wire straight back and forth. This causes abrasions on the cover. As you move back and forth, apply pressure with the thumb on the next parallel spot of the wire insert. Use a needle nose pliers to get the last tip into the channel. The next wire insert does not have to be overlapped.

For more details and to watch an illustration, please see our YouTube Video below